APPP Projects < $50,000 or > $1 Million
The constrained budget approach used for this study was a two-tiered approach. The first constraint placed caps on the annual statewide budget funds that could be spent on all airports ($3.5 million annually). The second constraint placed a cap of $1 million and a minimum of $50,000 on the amount of money a single eligible airport could receive in a given year. Because of this secondary constraint, it was important to identify any recommended projects that were expected to cost more than $1 million or less than $50,000. A summary of those identified projects is presented in the table below.
Table 1. Summary of APPP projects that exceeded $1 Million or were less than $50,000 under unlimited budget analysis.Year | Airport Name | Branch | Section | Work Type | Estimated Cost |
---|
2019 | Grand Canyon West | HP02PS | 10 | PCC Joint Reseal | $1,000 |
2019 | Rolle Airfield | HP01RL | 10 | PCC Joint Reseal | $1,000 |
Total Estimated Cost for 2019: | $2,000 |
2020 | Ak-Chin Regional | TWA3AC | 20 | 1-inch AC Overlay | $29,000 |
2020 | Bagdad | TWABG | 10 | 1-inch AC Overlay | $15,000 |
2020 | Eloy Municipal | TWAEM | 20 | 1-inch Mill/1-inch AC Overlay | $29,000 |
2020 | Phoenix Deer Valley | TWADV | 60 | 1-inch AC Overlay | $15,000 |
2020 | Phoenix-Mesa Gateway | TWAWG | 50 | PCC Joint Reseal | $11,000 |
2020 | Phoenix-Mesa Gateway | TWEWG | 10 | PCC Joint Reseal | $19,000 |
2020 | Phoenix-Mesa Gateway | TWGWG | 70 | PCC Joint Reseal | $16,000 |
2020 | Scottsdale | TWASC | 50 | 1-inch AC Overlay | $10,000 |
2020 | St. Johns Industrial Air Park | TWASJ | 30 | 1-inch AC Overlay | $39,000 |
Total Estimated Cost for 2020: | $183,000 |
2021 | Colorado City Municipal | TWBCL | 20 | 1-inch AC Overlay | $7,000 |
2021 | Falcon Field | RW4R22LMF | 10 | 1-inch Mill/1-inch AC Overlay | $1,095,000 |
2021 | Phoenix Goodyear | RW321GY | 10 | PCC Joint Reseal | $9,000 |
2021 | Phoenix Goodyear | TWA2GY | 20 | PCC Joint Reseal | $11,000 |
2021 | Phoenix-Mesa Gateway | TWGWG | 30 | PCC Joint Reseal | $6,000 |
2021 | Yuma International | TWZYM | 05 | 1-inch AC Overlay | $23,000 |
Total Estimated Cost for 2021: | $1,151,000 |
2022 | Casa Grande Municipal | RW523CG | 10 | 1-inch Mill/1-inch AC Overlay | $1,064,000 |
2022 | Glendale Municipal | RW119GL | 10 | 1-inch AC Overlay | $1,332,000 |
2022 | Laughlin/Bullhead International | TWA5LB | 10 | 1-inch AC Overlay | $30,000 |
2022 | Phoenix Deer Valley | TWBDV | 50 | 1-inch AC Overlay | $9,000 |
2022 | Phoenix Deer Valley | | 60 | 1-inch AC Overlay | $8,000 |
2022 | Phoenix Goodyear | TWA2GY | 10 | 1-inch Mill/1-inch AC Overlay | $10,000 |
Total Estimated Cost for 2022: | $2,453,000 |
2023 | H.A. Clark Memorial Field | HP01WI | 10 | 1-inch AC Overlay | $7,000 |
2023 | Whiteriver | TWBWH | 10 | 1-inch AC Overlay | $15,000 |
2023 | Yuma International | TWZYM | 40 | 1-inch AC Overlay | $30,000 |
Total Estimated Cost for 2023: | $52,000 |
2024 | Phoenix Deer Valley | TWA04DV | 10 | 1-inch AC Overlay | $16,000 |
2024 | Phoenix Deer Valley | TWCDV | 60 | 1-inch AC Overlay | $11,000 |
Total Estimated Cost for 2024: | $27,000 |
Total Estimated Cost for 2019-2024: | $3,868,000 |